Rail passengers across Denmark should expect delays and cancellations from Monday 16 November. DSB information chief Tony Bispeskov told Ritzau that the changes mainly affect Funen and Zealand. He stressed that the vast majority of trains still run as normal.

What is changing on Danish trains from Monday 16 November?

From Monday 16 November, DSB is running slower and fewer trains on parts of the network, mainly between Odense and Fredericia and at several points on Zealand. The changes are expected to last until 29 November and follow an unusually high number of rail defects found by Banedanmark.

Route What changes What passengers can do
Odense to Fredericia Regional trains replaced by buses in both directions Use the buses or InterCity services, which run with delays
Copenhagen, Funen and Fredericia Lower speeds, about 15 minutes longer travel time Allow extra time on the main route
Copenhagen to Næstved Trains run only between Køge Nord and Næstved Take the S train from Køge Nord to Copenhagen
Helsingør to Copenhagen Express trains cancelled in rush hour Check Rejseplanen for other departures

What happens between Odense and Fredericia?

Regional trains between Odense and Fredericia are replaced by rail replacement buses in both directions. InterCity and InterCityLyn trains still run on the line but with delays. DSB expects around 15 minutes of extra travel time on the main route between Copenhagen, Funen and Fredericia because trains must run slower.

Which services change on Zealand?

Trains between Copenhagen and Næstved will only run between Køge Nord and Næstved, so passengers heading to Copenhagen from Køge Nord should take the S train. Express trains between Helsingør and Copenhagen are cancelled during rush hour. Speed restrictions also apply at several locations on Zealand.

Why is DSB running slower?

The cause is Banedanmark, the rail infrastructure manager, which has registered an extraordinary number of rail defects. In its ongoing inspections this year it found 50 percent more defects than in a normal year. Where defects are found, trains must run at reduced speed. Typical restrictions are around 80 km/h, against up to 180 km/h normally.

Will the changes last beyond 29 November?

The changes are expected to run until 29 November, after which it will be assessed whether normal traffic can resume. DSB says further changes after that date are possible. It will adjust its timetable as Banedanmark repairs the defects that cause the speed restrictions.

What should passengers do and can they claim compensation?

DSB urges passengers to check Rejseplanen before travelling during the period. Most trains run as normal, but any train can be delayed where speed restrictions apply. Passengers delayed by more than 30 minutes can apply for the Rejsetidsgaranti, DSB’s travel time guarantee, through DSB.

FAQ

Until when will DSB run slower trains?
The changes are expected to last until 29 November. After that date it will be assessed whether normal traffic can resume, and further changes are possible.

Are regional trains running between Odense and Fredericia?
No. Regional trains on this stretch are replaced by buses in both directions. InterCity and InterCityLyn trains still run but with delays.

How much longer will the trip between Copenhagen and Fredericia take?
DSB expects around 15 minutes of extra travel time on the main route between Copenhagen, Funen and Fredericia.

Can I get compensation if my train is late?
Passengers delayed by more than 30 minutes can apply for the Rejsetidsgaranti through DSB.