Stockholm’s metro expansion is running late and will cost 23 billion kronor more than planned, according to Region Stockholm’s final cost forecast, presented on Friday. The total bill now stands at 99.8 billion kronor, or 22.9 billion above the original plan, an overrun of almost a third.
A schedule with no room for error
Per Ling-Vannerus, head of the administration for the expanded metro, describes the situation as unique, pointing to a schedule that was under heavy time pressure from the start and the fact that the project never had any risk reserves built into the original Stockholm Agreement.
Four reasons behind the overrun
Ling-Vannerus attributes the budget overrun to four main factors: rising construction costs since the project began, a buffer set aside for future risks, risk outcomes that have already materialised, and the additional time needed before the new metro stations can open.
Station openings pushed back
Several of the planned station openings are being postponed. Barkarby and Arenastaden will open a year later than planned, in 2029, while the extension to Nacka and the southern suburbs, originally due to open in 2030, will have to wait two years. The line to Älvsjö is not expected to be in operation until 2037.